KLSH recommends the suspension of the process of demolition of educational facilities, Municipality of Durrës

04.09.2020


Following the concern of the parent community and the media regarding the process of demolition of educational facilities in the Municipality of Durrës, the Supreme State Audit (ALSAI) has launched a thematic audit in the institutions of the

Ministry of State for Reconstruction and the Municipality of Durrës.

The object of the audit is the implementation of legal procedures in relation to Decision no. 32, dated July 02, 2020 of the State Commission for Reconstruction, regarding the educational facilities of the Municipality of Durrës, which are included in the list of facilities that will be reconstructed and reconstructed.

This audit started on August 31, 2020 and ends on October 01, 2020.

Given that the object of this audit is the legality of the decision-making of the classification of educational facilities needed to be reconstructed / reconstructed, therefore the object of this audit is the field verification of these facilities.

In the conditions when the audit group of ALSAI, which is conducting field verification of facilities, has been informed that, for some of the educational facilities provided in Decision no. 32, dated July 02, 2020 of the State Commission for

Reconstruction, as objects to be reconstructed, it was announced the release of the premises within 10 days and the relocation of the teaching activity to other premises, we have recommended the suspension of the process of demolition of educational facilities of Durrës Municipality , which are classified as objects to be reconstructed / reconstructed, until October 01, 2020. This deadline which coincides with the completion of the ALSAI audit.